Entergy Continues to Invest in Indian Point in Advance of 2020-21 Shutdown

Entergy’s Indian Point Unit 3 nuclear power plant began its 20th and final refueling and maintenance outage when control room operators removed the reactor from service on March 11.
Entergy is investing over $70 million in the plant during the refueling outage, which demonstrates the company’s ongoing commitment to Indian Point through permanent shutdown. The company announced in January 2017 the permanent shutdown of Unit 2 by April 30, 2020 and Unit 3 by April 30, 2021.
“The investments we are making at Unit 3 over the next several weeks demonstrate Entergy’s continued commitment to the highest standards of safety and reliability,” said Tony Vitale, site vice president and Entergy’s top official at Indian Point. “Our dedicated employees, whether they have worked at the site for four years or 40 years, are focused on making the last refueling our best ever. The nearly 60-year history of safe and reliable operations at the site is our legacy.”
About 900 skilled tradesmen and women contract workers will supplement nearly 1,000
Entergy employees during Unit 3’s outage to complete the refueling and other maintenance projects, which include:
• reactor head inspections
• comprehensive baffle bolt inspections (on a removable liner inside the reactor)
• reactor coolant pump seal replacements
• laser scans of the reactor head seal seating surfaces
• multiple pump and motor replacements
• emergency diesel generator preventive maintenance
Entergy has invested more than $1.3 billion in safety and reliability enhancements at Indian Point over the past two decades to ensure the generation of hundreds of millions of megawatt hours of nearly carbon-free power. Through philanthropic support, volunteerism, and environmental stewardship, Entergy has donated tens of millions of dollars to local community organizations throughout the region.
Similar News Items
Westchester Magazine recently featured the work of the Clean Energy Action Coalition’s (CEAC) Workforce Working Group in an article that explores the burgeoning field of clean energy workforce training and local initiatives that prepare residents for high-demand “green-collar” careers. The article emphasizes that as New York State pushes toward ambitious climate goals, the need for […]
BCW Member Wartburg, a senior care and housing provider in Mount Vernon, announced this week that ArchCare, the continuing care system of the Archdiocese of New York, have entered into an agreement to integrate the operations of Wartburg’s multi-facility healthcare and senior living campus into ArchCare. Under the agreement, which is subject to regulatory and […]
In a unique partnership to expand affordable access to nursing education, BCW Members Monroe University of New Rochelle and Richmond Community Services of Mount Kisco have announced a new workforce development partnership to create an innovative, accelerated pathway for Richmond employees to earn their Licensed Practical Nurse (LPN) credentials in just one year. The program […]
Become A Member
Join the county’s largest and most influential business organization today.
JOIN NOW!
Leave a Comment
You must be logged in to post a comment.